The following projects are currently under construction throughout the City. For more detailed information on any of the projects listed below. Stay tuned for more updates on upcoming projects.


Bickmore Avenue

Update 6/15/19
Work continues on Bickmore Avenue at a steady pace. The plan for completion is the week of July 22nd as the contractor encountered an unmarked Communications line, continued water intrusion into the trench, a broken water main, and the recent rain storm in mid May which slowed the progress of work. The crew is currently in the process of repaving about 300 feet of Bickmore now and will continue to proceed westerly into early July.

Thank you for your patience as we work with KB Homes to get Bickmore back to safe and driveable conditions.

Update May 4
After extensive testing at the site of the sinkhole on Bickmore Avenue, a plan for repairs has been drafted and work has already begun. 

The initial phase of the plan will focus on sewer work, then concurrent work will begin on the storm drain and finally street repairs will take place during the last phase of work. Much of the work will be completed 20 feet underground and over 1,000 feet in length.
During the duration of the project, work is being observed and inspected by the City and testing of the soil is on-going. The work is scheduled to be completed in approximately 60 calendar days but may be shortened depending on the amount of groundwater encountered.

We realize this is a significant inconvenience to those living and traveling in the surrounding area and we sincerely appreciate your patience as we work to get Bickmore back to safe and driveable conditions.

Kimball Avenue Mill Creek to Flight

Improvement work is scheduled to begin on Monday, May 6, 2019 on westbound Kimball Avenue between Mill Creek Avenue and Flight Avenue. 

The improvements consist of widening Kimball to include an additional westbound travel lane, the installation of a new traffic signal at Flight and Kimball Avenue and improvements to the center Median. 

To accommodate heavier traffic flow in the area, the closure will occur between 9:00am-5:00pm, Monday-Friday and overnight on Fridays. The project is scheduled to conclude Friday, June 11, 2019.

Kimball & Euclid

Improvement work is scheduled to begin Monday, May 13 on westbound Kimball Avenue at the intersection of Kimball and Euclid Avenue.

The improvements consist of widening Kimball to include an additional westbound travel lane and the installation of a curb and sidewalk. 

Work will take place between 9:00am-4:30pm and will NOT require a road closure. The project is scheduled to conclude Monday, June 24.

Stay tuned for continued improvements this summer on Kimball Avenue and Euclid and the intersection of Bickmore and Euclid. For more information, please call 909-334-3269.

City of Ontario Road Closure

The City of Ontario has closed the following roads to conduct needed repairs and to widen the roads:

1. Merrill Avenue between Archibald Avenue and Carpenter Avenue in both directions until January 20.

2. Northbound Carpenter Avenue will be intermittently closed between Merrill Avenue and Remington Avenue (time frame unknown).